The community of Feldkirchen intends to build a residential complex with lunchtime care, multifunctional room, 2 clusters of senior citizens' homes and an underground car park.
The planning site is located in a residential area that is adjacent to the special use in the east.
In the north, the railway line represents a border with the adjoining industrial park.
The proposed structures encompass a shared courtyard in a relaxed position, which forms the center of the quarter.
The publication includes drywall works:
— Start of execution: 8.2.2022,
— Completion: 14.11.2022.
Core quantities:
— metal stud walls (CCB, CCBI, H-GKFI) approximately 3 750 m
— metal stud firewalls (GM-F) approx. 6 m
— installation walls (CCB, CCBI, H-GKFI) approx. 550 m
— attachment shells (CCB, CCBI, H-GKFI) approximately 520 m
— shaft walls (GKF) approx. 5 m
— dry plaster (CCB) approx. 20 m
— acoustic wall panels approx. 37 m
— suspended acoustic ceilings (CCB, CCBI) approx. 590 m
— suspended plasterboard ceilings without /with fire safety requirements F0 — F90 (GKB, CCI, GKFI, GKF) approximately 1 170 m