Finsing Primary and Middle School; Extension of the west wing
VE 304 – Dachabdichtungsarbeiten
Roof waterproofing work:
01. Roof waterproofing work – flat roof over upper floor
01.01 Vapour barrier and insulation coatings
- Vapor barrier elastomer bitumen - Welding membrane total approx. 1,200 m²
- Thermal insulation layer PUR/ PIR rigid foam, sloping insulation layer 2-layer total approx. 1,200 m²
01.02 Substructures attic
- Attic formation in several parts on roof edges,
Width 50 – 110 cm incl. insulation work in total approx. 180 m
01.03 Waterproofing of flat roofs
- Roof waterproofing 2-layer polymer bitumen membrane total approx. 1,200 m²
01.04 Drainage facilities
- Drain flat roof attic pressure flow approx. 12 pieces
- Emergency drain flat roof attic pressure flow approx. 10 pieces
- Downspout metal, circular, steel stainless steel total approx. 100 m
01.05 Safeguards and covers – plumbing
- Attic cover aluminum total approx. 180 m
01.06 Protective coatings and extensive green roofs
- Protective layer roof waterproofing glass fleece with gravel fill approx. 300 m²
- Extensive green roof approx. 900 m²
02. Dacheinbauteile, Sicherungseinrichtungen
02.01 Dachdurchführungen
- Cable grommet gooseneck total approx. 4 pieces
02.02 Anseilsicherung Überfahrbar
- Rope protection, drive-over rope length, 160 m 1 flat rate
03. Abdichtungsarbeiten
03.01 Detailed waterproofing and miscellaneous
- Joints and terminations, waterproofing, liquid plastic, total approx. 120 m