The procurement procedure used is: the open invitation to tender. It is subject to the provisions of articles L. 2124-2, R. 2124-2 1º and R. 2161-2 to R. 2161-5 of the public procurement code.
This consultation concerns:
Creation of a football complex at par du Loret in Cenon — it consists of sixteen lots.
The project includes the creation of two football fields in synthetic surface, half grass terrain, the construction of a sports pole building, a technical pole building, access roads and car parks.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code.
— the work will be carried out in co-activity;
— companies will be forced to work in the summer period.
Earthworks - VRD - green spacesEarthworks — HRD — green spaces.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP. Compliance with these provisions is a condition of the conformity of the offer.
For lots 1, 2 and 3, the judgment of tenders shall incorporate, in the context of weighting the selection criteria, a measure of the quality of execution of the insertion clause based on:
— the number of additional insertion hours proposed by the candidate (four points);
— technical support (six points);
— socio-professional support (six points);
— the rise in skill and training (four points).
DrywallWork on laying drywall.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Interior wood carpentry — false ceilingLaying work of interior wood carpentry and false ceilings.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Tiles - earthenwareWork on laying tiles and earthenware.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Painting - flooringPainting work and laying floor coverings.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
ElevatorInstallation work of an elevator.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
Electricity strong and weak currentsStrong and weak electrical work.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Heating - ventilation - plumbing - sanitaryHeating - ventilation - plumbing - sanitary.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Sports floors — furniture — fences — balloon screensWorks and equipment: sports floors — furniture — fences — balloon screens.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP. Compliance with these provisions is a condition of the conformity of the offer.
For lots 1, 2 and 3, the judgment of tenders shall incorporate, in the context of weighting the selection criteria, a measure of the quality of the execution of the insertion clause based on:
— the number of additional insertion hours proposed by the candidate (four points);
— technical support (six points);
— socio-professional support (six points);
— the rise in skill and training (four points).
Big workStructural work
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP. Compliance with these provisions is a condition of the conformity of the offer.
For lots 1, 2 and 3, the judgment of tenders shall incorporate, in the context of weighting the selection criteria, a measure of the quality of the execution of the insertion clause based on:
— the number of additional insertion hours proposed by the candidate (four points);
— technical support (six points);
— socio-professional support (six points);
— the rise in skill and training (four points).
Metal frameMetal frame work.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
BlanketRoof works.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
sealingSealing work.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.
Wood sidingWood cladding work.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Aluminum exterior carpentryCarpentry work.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022. This consultation includes conditions of execution of a social nature, according to Articles L. 2112-2 and L. 2152-7 of the new public order code, the details of which are indicated in the CCAP.
Locksmithing and stands seatsLocksmithing work and installation of stands seats.
The overall maximum time limit for the completion of the work is 12 months including the summer period, with a mandatory delivery deadline at the end of July 2022.