After completion of the first construction phase, the extension of the middle school (MS) is now taking place in a second construction phase, an increase in
of existing parts as well as supplementation of various areas and construction of a break hall between the new building, the gymnasium
and middle school. In addition, the collection of the middle school is to be completely refurbished. For this purpose, the building will be completely
cleared.
masses:
In the course of the energetic renovation of the middle school in Germering, extensive carpentry work is required,
which include the following services:
-Interior doors with and without fire protection requirements (wooden doors with block frames)
-window sills
-Interior windows with and without fire protection requirements
-media columns
-Wall signs behind washbasins
-Wall absorbers (acoustic panels)
-Various small components
Events:
W+M planning: 13.06.22 - 11.07.2022
Assembly start: 05.09.2022
Completion installation of interior doors: 14.11.2022
Completion Total: 12/12/2022