The Suzanne Lenglen court is one of the essential equipment of the Roland-Garros stadium. It has been designated by Paris 2024 as Olympic site to host the boxing events.
The setting up of a light and retractable cover on this court will allow to welcome the boxing tests in optimal conditions and will guarantee durably the good organization of the Roland-Garros tournament in case of inclement weather.
The purpose of this consultation is to entrust a third party with the design and implementation of this retractable cover.
Main constraints of the project:
- respect for the architectural writing of the court,
- maintenance of the classification in outdoor equipment, including when the cover is in the closed position,
- minimize the impact of work on the existing,
- respect of the delivery schedule of the Olympic works.
Annual organizational constraint of the RG tournament: the periods of possible work are between 2 editions (mid-June to the end of March of the following year).
The Suzanne Lenglen court is one of the essential equipment of the Roland-Garros stadium. It has been designated by Paris 2024 as Olympic site to host the boxing events.
The setting up of a light and retractable cover on this court will allow to welcome the boxing tests in optimal conditions and will guarantee durably the good organization of the Roland-Garros tournament in case of inclement weather.
The purpose of this consultation is to entrust a third party with the design and implementation of this retractable cover.
Main constraints of the project:
- respect for the architectural writing of the court,
- maintenance of the classification in outdoor equipment, including when the cover is in the closed position,
- minimize the impact of work on the existing,
- respect of the delivery schedule of the Olympic works.
Annual organizational constraint of the RG tournament: the periods of possible work are between 2 editions (mid-June to the end of March of the following year).