Interior plastering and painting work on the 4th construction phase of the general renovation of a grammar school
Interior plastering and painting work for the general renovation of a grammar school
Gross volume (BRI) BA IV:
(after refurbishment)
BT C: 5.881,50m³
In the course of the renovation, the existing walls of the building will be restored to their raw state, and some new walls will be created.
Main positions interior plaster:
- approx. 260 m² Wärmedämmputz
- approx. 450 m² lime-gypsum plaster
- approx. 23 m² Brandschutzputz
Main positions painting and varnishing work.
- approx. 2,400 m² tapping of walls and ceilings with silicate paint
- 6 pcs painting metal doors