Building project:
For the Helmholtz Center Potsdam, German Research Center for Geosciences, a new laboratory building with offices and server room is planned on the listed Telegrafenberg southeast of Potsdam city center. The gross floor area is approx. 3 850 m
Building automation with BACnet-IP, KNX and DALI for the new building A71 consisting of 6 focal points of information with a total of around 3000 data points for 8 air-conditioning systems, 27 laboratory regulations for maintaining a negative pressure as well as 31 office applications based on communication with KNX including cooling for one in the building Integrated data center with recooling systems and special software energy network with waste heat utilization and extensive energy self-sufficiency. 19 control cabinets for 6 information centers, 121 immersion temperature sensors, 56 air duct sensors, 58 presence detectors, 13 heat and cooling quantity meters.
Extension of the existing building management system of Siemens Desigo Insight V9 by 3000 data points and 95 operating graphics.
Delivery of 6 control valves, 43 variable volume flow controllers and 16 fume cupboard monitors with control panel. It is mandatory to carry out a conformity test for BACnet-IP with Desigo Insight V6 on site.