The measure includes services for special foundation engineering including earthworks and dredging work, solid construction, services for technical processing using BIM including preparation of as-built documents as well as services for functional tests and trial operation.
,
The tendered services for Lot 1 include the following main services:
- Technical processing using the BIM method
- Construction site equipment, preparatory work, production of the client's construction office
- Construction and dismantling of access roads to the central island during construction in the surface and underwater
- Demolition, dismantling and disposal of parts of the existing lock as well as (partial) filling of the existing west lock
- Replacement of the west lock in seamless construction under the protection of an excavation pit with braced bored pile walls or sheet pile walls and a back-anchored underwater concrete base (including all earthworks)
- Construction of the connecting sewer in seamless construction under the protection of a construction pit with stiffened sheet piling walls and a back-anchored underwater concrete base
- Adaptation of the entrance areas in the underwater as well as in the upper water in partial areas
- Construction of two technical buildings
- Adaptation of terrain and creation of traffic areas
- Construction of a new access road including a paved path
- trial run
- Technical processing, including the preparation of all documents required for the execution and commissioning of the lock, partly using the BIM method
- Coordination of the interfaces between the individual lots
- Preparation of inventory documents
- approx. 34,000 m³ reinforced concrete (lock structure)
- approx. 148,000 m³ of excavated soil (wet and dry)
- Installing approx. 70,000 m³ of soil (wet and dry)
- approx. 30,000 m² Oberbodenarbeiten
- produce approx. 9,000 m² of stiffened bored pile wall and
- ca. 43 St Stahlrohrsteifen (Schleusenbaugrube)
- approx. 6,000 m³ Unterwasserbetonsohle (Schleusenbaugrube)
- ca. 1.000 St. Mikropfähle (Auftriebssicherung Schleusenbaugrube)
- Deliver approx. 900 t of steel sheet piles
- Approx. 3,600 m² of anchored bank sheet pile wall
- ca. 25 St. Rundstahlanker
- ca. 57 St. Dauerverpressanker
- approx. 9,600 m² of road and path construction work, partly asphalted (on public roads, on the lock area, in the area of the outer harbours)
- Construction of two technical buildings