Finsing Primary and Middle School; Extension of the west wing
VE 301 - Earthworks
earthworks:
Nature and scope of the essential service:
01.Baustelleneinrichtung
01.01Construction site equipment of the Contractor
01.02Construction site security and protective measures
02. Demolition work and clearing of construction sites
02.01Demolition work surfaces
-EPDM - Breaking the flooring, picking upTotal approx. 1240 m²
02.02Clearing construction site
-Clearing rootstocks, digging upTotal approx. 15 pcs.
03.Erdarbeiten
03.01Ground work – preparatory work
-Clear vegetable ground coverTotal approx. 2760 m²
03.02Upper and lower floor
-Remove topsoil, dispose of it in partTotal approx. 850 m³
03.03Baugrubenaushub Zwischenbaugrube
-Loosen the intermediate excavation pit, dispose of it in partTotal approx. 2180 m³
03.04Production of work plan including ballast layer
-Supplying ballast, pavingTotal approx. 510 m³
03.05Bedding layer for BE surfaces and access roads
-Bedding layer provide filler, installTotal approx. 540 m³
03.06Backfill Building
- Fill the building, pour it overtotalapprox. 1735 m³