The overall project involves the renovation and extension of a three-field sports hall. The renovation concerns the roof surfaces, the façade surfaces and the interior fittings. In the course of the expansion, a single-storey extension will be built on the east side. On the south side, after the demolition of the old building, a new foyer area is being built for the main development of the three-field sports hall. The technical renovation concerns the heating, ventilation and sanitary facilities as well as the entire electrical engineering.
- Preparatory measures, such as surface cleaning and plaster repairs: approx. 150 m²
- Spachtelarbeiten ca. 150 m²
- Interior painting Initial coating walls and ceilings (different. Surfaces): approx. 2,760 m²
- Interior painting of existing surfaces Walls (different. Surfaces): 1.500 m²
- 2K – epoxy resin coating on acoustic brick walls: approx. 400 m²
- 1 K - acrylic concrete paint hall truss: approx. 1,100 m²
- 2 K – epoxy resin floor coating: approx. 70 m²
- Metal coatings on the inside: approx. 270 m
- Metal paint railing inside: approx. 240 m
- Metal paint external staircase: 1 pcs
- Fire protection coating open profiles: approx. 45 m²