The procurement consists of the design and execution of a "Photovoltaic Park" and its connection to the electric power plant at AIHCB. The description of the works is available in the specifications document within this awarding documentation.
The estimated value of the contract is 134,614,800.00 lei excluding VAT. Additionally, a share of various and unforeseen expenses can be added, amounting to 5,384,300.00 lei, excluding VAT.
The duration of the contract is 60 months, with the term for design and execution being 18 months from the date specified in the start order issued by the beneficiary. The duration of the warranty period for the executed works is 36 months from the signing of the minutes of reception upon completion of the works.
Number of days until clarifications can be requested before the deadline for submission of offers: 18 days before the deadline for submission of offers. The contracting entity will respond to all requests for clarification received on the 11th day before the submission deadline for offers.
LOT-0000
Default lot.
The procurement consists of the design and execution of a "Photovoltaic Park" and its connection to the electric power plant at AIHCB. The description of the works is available in the specifications document within this awarding documentation.
The estimated value of the contract is 134,614,800.00 lei excluding VAT. Additionally, a share of various and unforeseen expenses can be added, amounting to 5,384,300.00 lei, excluding VAT.
The duration of the contract is 60 months, with the term for design and execution being 18 months from the date specified in the start order issued by the beneficiary.
The duration of the warranty period for the executed works is 36 months from the signing of the minutes of reception upon completion of the works.
The implementation duration of the contract is conditioned by the provisions of the financing contract, and the project is to be completed within a maximum of 24 months from the date of signing the financing contract, specifically by 23.12.2025, which prevails in the event of any discrepancies regarding the execution schedule.
Number of days until clarifications can be requested before the deadline for submission of offers: 18 days before the deadline for submission of offers. The contracting entity will respond to all requests for clarification received on the 11th day before the submission deadline for offers.