New Waldorf School Dresden,
New building BA1 lunch house and middle school house
Lot 12 - Painting
New Waldorf School Dresden,
New building BA1 lunch house and middle school house
Lot 12 - Painting
In the course of the first construction phase of the New Waldorf School Dresden, two buildings will be erected. The lot includes the painting work inside for the two buildings: Mittagshaus and Mittelstufenhaus.
Painting work inside: a total of approx. 3,000 m² of multi-layer paint with coloured tinted colours on a mineral basis on GK wall and ceiling surfaces
Impregnate a total of approx. 6,500 m² of exposed concrete wall surfaces and ceiling surfaces on a silicate basis
approx. 350 m² floor coating epoxy resin
approx. 80 m² of primed stair railings on site
ca. 35 m² Aufzugsportale endbeschichten
approx. 50 m² steel paved parts first coated
Painting work outside:
Approx. 160 m² exposed concrete surfaces on the outside colourless protective coating
Approx. 25 lfm step edge markings on precast reinforced concrete stairs