The project includes:
— Upgrading of electric and control technical installations in the Mundalsberg and Bjørsvik tunnels.
Main quantities in the Mundalsberg tunnel:
— Traffic management with traffic management vehicles;
— 9 SOS cabinets;
— 1 emergency station kiosk;
— 1 technical building;
— 44 guiding lights;
— 258 lighting fixtures;
— 1 130 m cable racks;
— 2,2 km fibre cable;
— 1 100 m radiating cable;
— 2 200 m coax cable;
— 6,6 km cable conduit.
11 conduit manholes.
— 24 signs;
— 4 variable signs;
— 2 red blinking lights;
— 2 barriers with loops and cameras;
— 1 082 guardrails made of concrete, inside the tunnel;
— 55 m guardrails made of concrete, in open air;
— 1 700 m² PE foam;
— 450 m³ shotcrete;
— 570 support bolts;
— 20 m² dry wall;
— 250 m³ blasting in open air.
Main quantities in the Bjørsvik tunnel:
— Traffic management with traffic management vehicles;
— 6 SOS cabinets;
— 2 emergency station kiosk;
— 1 technical building;
— 34 guiding lights;
— 2,6 km low-voltage cables;
— 1,1 km fibre cable;
— 850 m radiating cable;
— 910 m coax cable;
— 2,4 km cable conduits.
11 signs.
— 4 variable signs;
— 2 red blinking lights;
— 2 barriers with loops and cameras;
— 202 m railings with metal rails;
— 845 m guardrails made of concrete, in tunnel;
— 137 m guardrails made of concrete, in open air;
— 5 600 m² PE foam;
— 600 m³ shotcrete;
— 2 000 support bolts;
— 50 m³ blasting in tunnel;
— 100 m³ blasting in open air.