Demolition and dismantling work on the 4th construction phase during the general renovation of a grammar school
Building clearance, dismantling, dismantling and demolition work for the general renovation of a high school.
Gross volume (BRI) BA IV:
(after refurbishment)
BT C: 5.881,50m³
Dismantling / demolition:
In the course of the demolition and dismantling work, the existing building will be largely restored to its shell condition. First
the remaining furniture and furnishings are cleared and floor coverings and elements to be preserved are provided with protective coverings.
Main positions:
– Protective devices and safety devices
– approx. 625 m2 demolition ceiling plaster reed,
– approx. 55 m removal/disposal of pipes containing asbestos,
– approx. 600 m demolition/disposal pipelines,
– approx. 110 hours of demolition/disposal of various radiators,
– approx. 2,450 m demolition/disposal of various electrical cables,
– approx. 22 hours of demolition/disposal of various doors,
– approx. 120 hours of demolition/disposal of various windows,
– approx. 95 m2 demolition/disposal of glass blocks,
– approx. 1,050 m2 demolition/disposal of various floor coverings (mainly containing asbestos) and screeds,
– approx. 1,270 m2 demolition/disposal of various wall coverings,
– approx. 470 m2 demolition/disposal of various ceiling coverings