Schadstoffsanierung (23 and 0257)
Pollutant remediation work
- Timeframe: approximately from October 2023 to January 2024
- the work is carried out in sections
Short description:
- Dismantling and disposal of KMF insulation in sloping roofs,
on ceilings and partly in drywall constructions - approx. 3.160m
- Dismantling and disposal of drywall - approx. 70m
- Dismantling and disposal of "Toschi" pipes - approx. 120 m
- Dismantling and disposal of pipeline insulation (elastomer foam) - approx. 890 m
- Dismantling and disposal of pipeline insulation (MiWo, KMF) - approx. 3,095 running metres
- Dismantling and disposal of finned radiators with asbestos seals - approx. 161pcs
- Dismantling and disposal of wooden structures (platform, color coated) - approx. 15.5m
- Dismantling and disposal skirting boards (wood color coated) - approx. 1.919 running meters
- Dismantling and disposal of wall tiles - approx. 590m
- Dismantling and disposal of floor coverings: carpet approx. 90m
Tiles approx. 574m
- Dismantling and disposal of cement screed - approx. 1.255m
- Dismantling and disposal of asphalt screed with PAH - approx. 1.025m
- Dismantling and disposal of PAH-containing black waterproofing on bare ceilings and walls - approx. 1.038m
- Milling of rough slabs under broken asphalt screed - approx. 1.025m
- Sanding of bare ceilings under broken black waterproofing - approx. 574m
- Dismantling and disposal of tar cork insulation radiator niches - approx. 175m
- Dismantling and disposal of sheet steel doors - approx. 7pcs
- Dismantling and disposal of drywall cladding - approx. 49m