Trockenbauarbeiten
Installation of free-standing facing shell H = 3.75 m, approx. 18.00 m2
Installation of internal partition walls made of drywall H = 5.00m, d = 15cm, approx. 120.00 m2
Installation of internal partition walls made of drywall H = 3.60m to 5.00m, d = 15cm, approx. 100.00 m2
Installation of suspended ceilings made of drywall, span 3m, approx. 20.00 m2
Installation of openings in drywall in various sizes
Installation of reinforcements in substructure
Production of cut-outs / recesses in various sizes, approx. 40 pieces
Closing of various recesses, approx. 35 pieces
Production of surface reinforcement with fleece insert, approx. 450,00m2
Production of protective covers made of fleece and foil, each approx. 100.00 m2
Abklebeband, ca. 210,00 m
Wall painting gypsum board with emulsion paint, approx. 420.00 m2
Initial coating on wall with silicate paint, inside, plaster substrate, approx. 170.00 m2
Initial coating ceiling gypsum board with emulsion paint, approx. 11.00 m2
Primer interior wall, sand-lime brick substrate, approx. 170.00 m2
Filling with cement filler Q3, KS wall inside, approx. 170.00 m2
Number of storeys with spray paint, stencil, 7 pieces
Initial coating of concrete floor with cove, oil-resistant, approx. 55.00 m2
Impregnation floor screed, approx. 120,00m2
Coating floor screed with dispersion varnish, approx. 35.00m2
Concrete glaze stair parapets and soffit, potash water, approx. 85.00m2
Cloakroom locker made of sheet steel, lockable, HxWxD 1800 x 400 x 500 mm, 9x2 compartments, 1 piece