Earthworks, adaptation of excavation pit, shoring work
The subject of the tender is earthworks and shoring work as part of the construction of a school building and a sports hall.
This work includes the following areas:
-Earthworks and demolition works
-Construction site equipment earthworks
-Preparatory work demolition
-Kampfmittelsondierbohrungen
-Work out excavation
-Earthworks backfilling
-Verbauarbeiten
-Preparatory work
-Construction site set-up shoring work
-Girder plank wall with back anchoring
Main positions (school building and sports hall)
-Peel off the turf, removal approx. 3,200 m²
-Remove and dispose of topsoil approx. 3,200 m²
-Loosen the soil, store it temporarily, load it and dispose of it approx. 2.150 m²
-Grade after excavation approx. 5,800 m²
-Bedding layer, supply and install filler, 25 cm approx. 5,800 m²
-Frost protection layer, supply and install filler, 25 cm approx. 5,800 m²
-Sacrificial layer, 15 cm approx. 5,800 m²
-Demolition of drainage channel DN 110 - 200 approx. 400 m
-Excavation, exposure of the shafts approx. 160 m³
-Filling of the trenches approx. 200 m³
-Vertical bore piping approx. 450 m
-Vertical bore piping approx. 970 m
-Bore inclined approx. 250 m
-Extension, adaptation of a construction pit, dispose of house 3 approx. 3,800 m³
-Extension, adaptation of a construction pit, dispose of house 1-2 approx. 13,000 m³
-Extension, adaptation of a construction pit, dispose of sports hall approx. 1,870 m³
-Flat surface of the excavation pit, houses 1-2 & 3 approx. 1,750 m²
-Flat surface of the excavation pit, sports hall approx. 2,250 m²
-Protect the embankment of the excavation pit, houses 1-2 & 3 approx. 2,400 m²
-Protect the embankment of the excavation pit, sports hall approx. 1,200 m²
-Baugrubenverbau, Trägerbohlenwand ca. 230 m²
-Baugrubenverbau, Trägerbohlenwand ca. 314 m²
-Root area protection construction machinery, fleece approx. 120 m²