Structural work for the construction of a new processing unit for medical devices. The previous existing building has already been demolished.
Gross volume approx. 10,200 m3
Gross floor area approx. 2,200 m2
Reinforcement: approx. 180 t
Total measure: 10,200 m³ BRI / 2,200 m³ GFA
The supporting structure consists of clamped reinforced concrete columns on a solid concrete floor
(as a slab foundation), stiffening walls made of reinforced concrete,
Execution of the ceiling above ground floor as a prestressed reinforced concrete ceiling.
The roofs are built in steel construction and with trapezoidal sheet metal covering.
In the 1-storey area, a flat roof construction is formed, the roof of the staggered
Upper floor as a 2-nave gable roof construction.
The stiffening of the building is carried out by reinforced concrete walls and staircase cores, as well as by the
ceiling constructions formed as panels.
The façade is used as a clinker façade or rear-ventilated curtain façade construction with
Sheet metal cladding with plastic and aluminium windows.
The interior is carried out both in dry construction and in solid construction.