Description:
Complex rural electrification works - concealment and reinforcement of networks - period 2023 TO 2026

This consultation concerns studies and works, called complex, of electrification, namely:

- Concealment of electricity networks, mainly in LV, with removal of existing networks, construction of new lines, mainly underground, realization of connections,

- construction of HV and LV lines, in bare or insulated conductors, overhead or underground, Hta/Bt substations in cabins, bases or poles, and supply of transformers,

- reinforcement of overhead or underground networks,

- All induced works: civil engineering, public lighting network and installations, civil engineering for electronic communications networks, etc.

Geographic Lot 1

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations.

Geographic Lot 2

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

Geographic Lot 3

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

Geographic Lot 4

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

Geographic Lot 5

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

Geographic Lot 6

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

lot géograhique no 7

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

Geographic Lot 8

The projects to be carried out are characterized by a certain complexity and concern:

- All files of burial of networks with generally public lighting, civil engineering works for electronic communications, the resumption of existing connections, removal of high cabins,

- extensions of more than 1 000 metres of HVT network or implementing at least 2 Hta/Bt substations,

- Reinforcement files using more than 1,000 meters of HTA + BT network or implementing at least 2 Hta/Bt substations

Download full details as .pdf
The Buyer:
siceco
CPV Code(s):
32428000 - Network upgrade
45231400 - Construction work for electricity power lines