Energieversorgung Schwerin GmbH und Co. Generation KG is a 100% subsidiary of Stadtwerke Schwerin GmbH and has been operating a gas and steam turbine thermal power station at each of the Schwerin Süd and Schwerin Lankow locations since 1994.
The cogeneration plants put into operation in 1994 are to be modernized within the framework of the currently valid KWKG (in the version of 2017) - due to the advanced age of system parts and the energy requirements.
The modernization measures for the CHP plant in Schwerin Lankow essentially include the following measures:
- replacing the gas turbines with a Solar Titan 130,
- Conversion of the waste heat boiler from steam to hot water
- the resulting adaptation of waste heat boilers,
- the renewal of power plant control technology/electrical engineering as well as
- the modernization of further peripheral plant components.
The contractor must carry out two state-of-the-art 0.4kV low-voltage switchgear, with all accessories for proper and safe operation, including all necessary equipment for monitoring, protection, reporting, measurement and control.
These include, but are not limited to:
• Engineering,
• Manufacturing,
• Examination incl. FAT,
• transport and introduction,
• the complete assembly and upgrade,
• commissioning,
• the complete documentation in German,
• trial operation,
• acceptance.