The overall project consists of the energy and technical rehabilitation of the Roucas residence, located in Vitrolles, consisting of 212 housing units divided into 25 buildings on levels R+1, R+2 and R+3.
The tasks entrusted to the incumbent are as follows:
- Phase 1 : Diagnostic (Diag.)
- Phase 2: Preliminary design (APS)
- Phase 3: Final Preliminary Design (DPA)
- Phase 4: Project studies (Pro)
- Phase 5: Assistance with the award of works contracts (Amt)
- Phase 6: Total Execution and Synthesis Studies (Total Exe including Visa)
- Phase 7: Construction Execution Directorate (DT)
- Phase 8: Scheduling, Piloting and Coordination (OPC)
- Phase 9: Assistance with receiving operations (Aor including Doe)
- Phase 10: complementary mission: Social project management (MOS)
- Phase 11: additional mission: Diagnosis of the products, equipment, materials and waste resulting from the rehabilitation operation and verification form (PEMD)
The overall project consists of the energy and technical rehabilitation of the Roucas residence, located in Vitrolles, consisting of 212 housing units divided into 25 buildings on levels R+1, R+2 and R+3.
The tasks entrusted to the incumbent are as follows:
- Phase 1 : Diagnostic (Diag.)
- Phase 2: Preliminary design (APS)
- Phase 3: Final Preliminary Design (DPA)
- Phase 4: Project studies (Pro)
- Phase 5: Assistance with the award of works contracts (Amt)
- Phase 6: Total Execution and Synthesis Studies (Total Exe including Visa)
- Phase 7: Construction Execution Directorate (DT)
- Phase 8: Scheduling, Piloting and Coordination (OPC)
- Phase 9: Assistance with receiving operations (Aor including Doe)
- Phase 10: complementary mission: Social project management (MOS)
- Phase 11: additional mission: Diagnosis of the products, equipment, materials and waste resulting from the rehabilitation operation and verification form (PEMD)