DRK Pain Center Mainz, 2nd BA - Modernization of old building: heat supply systems for construction phase 2.2.
The present tender describes the technical disassembly and new installations in the heat supply systems trade in an existing hospital. The relevant construction phase is connected to transfer points that have already been set up.
Before the start of dismantling, the executing company must find out about the technical systems and set up any temporary measures required for the further use of the hospital operation.
- Dismantling of approx. 1 300 m heating pipes, including insulation;
- Disassembly of approx. 135 radiators;
- Installation and connection of approx. 100 radiators;
- laying approx. 1 350 m steel pipe DN 15-20;
- laying approx. 300 m steel pipe DN 25-32;
- Lay approx. 100 m steel pipe DN 40-50.