The subject of the contract is the supply of electricity to the Wrocław Stadium in Wrocław at Al. Śląskia 1, in the amount of about 2,400 MWh, for a period of 6 months (01.01.2023 – 30.06.2023), with a capacity of
Ordered:
- PPE power supply NR 590322415104135385 (SI connection, 20kV) - 1 000 kW
- PPE power supply NR 590322415104090096 (SII connectors, 20kV) — 900 kW
Connection group: III.
Tariff group: B23.
Measurement and billing system installed at 20kV voltage in R-3808.
The subject of the contract is the supply of electricity to the Wrocław Stadium in Wrocław at Al. Śląskia 1, in the amount of about 2,400 MWh, for a period of 6 months (01.01.2023 – 30.06.2023), with a capacity of
Ordered:
- PPE power supply NR 590322415104135385 (SI connection, 20kV) - 1 000 kW
- PPE power supply NR 590322415104090096 (SII connectors, 20kV) — 900 kW
Connection group: III.
Tariff group: B23.
Measurement and billing system installed at 20kV voltage in R-3808.
2. The estimated amount of energy ordered given in point 1 above is indicative, used to compare offers and does not constitute an obligation on the part of the Ordering Party to purchase energy in the given quantity.
The Contractor shall not be entitled to any claim for the Ordering Party's failure to consume the expected amount of energy.
3. Any change in the expected estimated consumption will not result in additional costs for the Ordering Party, apart from settlement for the amount of energy actually consumed according to the prices specified in the documentation.
Tender.
4. The energy supplier is obliged to have a distribution agreement concluded with the Distribution System Operator (DSO) by the date of conclusion of the contract regarding the contract in question at the latest.
appropriate for the Ordering Party's facilities.