The 1st construction phase of the coastal grammar school in Neustadt in Holstein has been completed.
This is followed by the 2nd construction phase.
For this purpose, one building is demolished and two buildings gutted, which in turn contain a partial demolition. In the gutted buildings, the statically relevant walls, ceilings and columns remain.
1st construction phase
The 1st construction phase is completed by the new building.
This allows the measure required for the 2nd construction phase to begin.
2nd construction phase
2.1 Demolition of tract 4
2.2 Renovation of tracts 1 and 8, including construction and enclosure (HLS u. E) UG Trakt 1, after completion relocation to the buildings.
Expected construction period: April 2023 to June 2025
3rd construction phase
3.1 Demolition of sections 5 and 6
3.2 Renovation of the sports halls wing 7 and 9, including the preparation of the outdoor facilities.
Estimated construction period: June 2025 to Dec. 2026
4. Development:
Access to the construction site is via Sandberger Weg, Butzhorn - Kreisel directly to the demolition site for demolition work in Neustadt.
5. Information on existing components:
-Tract 4
The load-bearing structure consists of reinforced concrete with masonry infills. The façades partly consist of clinker façades and perforated window facades.
This building will be completely demolished.
-Tract 8
The building is gutted, i.e. the façade and the internal fixtures are demolished, leaving only the columns and the phi ceilings. In the inner courtyard, a canteen, with a steel construction and glass façade, has been installed, which will be completely demolished.
-Main entrance
The main entrance consists of a steel structure with a gasabeton ceiling, glass façade and a reinforced concrete base that is completely demolished. The pile foundation connected to the sole is retained.
-Side entrance
The side entrance with its reinforced concrete walls, staircases, glass facades and reinforced concrete ceilings will be completely demolished.
site equipment
safeguards
Micro bored piles 1 pc.
Earthworks approx. 300 m
Drainage/infiltration approx. 240 m
Drainage
Concrete work approx. 250 m
Demolition wall plaster
Verblendmauerarbeiten ca. 800 m
Waterproofing
underground pipes
Concrete renovation