The construction project of line 302 includes the construction phase between
Watermann's way. to the stop Lohrheidstr.
The total construction project amounts to approx. 650m.
The construction project extends over two separate construction phases
BA1 from Watermanns Weg to Hollandstr.- BA2 from Hollandstr. to bus stop
Lohrheidestr.
In both construction phases, the new catenary system must be adapted to the existing catenary system.
On the outer masts, transverse spans as well as double-track booms are installed for a
track and mounted for two tracks. The production of the masts and the delivery of the masts are not part of this
Call for tenders, this will be advertised separately.
The contractor has the obligation to coordinate the delivery in consultation with the mast supplier and BOGESTRA AG.
The construction project of line 302 includes the construction phase between
Watermann's way. to the stop Lohrheidstr.
The total construction project amounts to approx. 650m.
The construction project extends over two separate construction phases
BA1 from Watermanns Weg to Hollandstr.- BA2 from Hollandstr. to bus stop
Lohrheidestr.
In both construction phases, the new catenary system must be adapted to the existing catenary system.
On the outer masts, transverse spans as well as double-track booms are installed for a
track and mounted for two tracks. The production of the masts and the delivery of the masts are not part of this
Call for tenders, this will be advertised separately.
The contractor has the obligation to coordinate the delivery in consultation with the mast supplier and BOGESTRA AG.