Description:
Helicopter Transportation Services.

Supply of helicopter transport services for transport of personnel between Norden airport (alternatively Emden airport or another airfield in the area) and the offshore Borkum Riffgrund Windfarm 1 during the installation of the wind-turbines and during the operation and maintenance phase and possibly the same services for the offshore Borkum Riffgrund Windfarm 2.

The frame agreement will include offshore/hoisting operations on offshore substation and wind-turbines foundations/transition pieces.

The following needs are expected (indicative/subject to change):

A) Offshore wind-farm Borkum Riffgrund 1 - Installation of wind-turbines phase

1) Flights between Norden and offshore sub-station (landing on offshore sub-station helideck)

1.1) Period: 1.8.2013 -> 1.1.2014

2 flights per day morning and afternoon + availability whole day– 7 days a week

Capacity min 5 pax.

1.2) Period: 1.1.2014 -1.8.2014

2 flights per week (morning + return in the evening)

Capacity min 5 pax.

1.3) Period: 1.8.2014 - 1.12.2014

2 flights per day morning and afternoon + availability whole day – 7 days a week

Capacity min 5 pax.

2) Hoisting to transition pieces (wind turbine foundation before the installation of the wind-turbine)

— Period: 1.4.2014 -> 1.9.2014.

— 2 flights per week (morning + return in the evening).

— Capacity min 4 pax.

3) Transport to offshore sub-station and hoisting to wind-turbine

Period: 1.9.2014 -> 28.2.2015.

2 flights per day morning and afternoon + availability whole day – 7 days a week

Capacity min 4 pax.

B) Offshore wind-farm Borkum Riffgrund 2 - Wind-turbines installation phase

All above operations to be performed 10 month later than above.

C) Operation & Maintenance phase for offshore wind-farm Borkum Riffgrund 1

Hoisting to wind-turbines and transport to offshore sub-station from Norden.

Period: 1.9.2014 until 1.4.2015.

Frequency: Summertime low, wintertime high.

Max expected flying hours per year: 400 (progressive increase).

Capacity min 4 pax.

D) Operation & Maintenance phase for offshore wind-farm Borkum Riffgrund 1 & 2

Hoisting to wind-turbines and transport to offshore sub-station from Norden landing base.

Period: 1.7.2015 - 31.12.2016 (progressive increase).

Frequency: Summertime low, wintertime high.

Expected flying hours total/year when max.: 700.

Capacity min 4 pax.