Demolition and disposal of outdoor facilities, clearing, dismantling and disposal of equipment, complete demolition and disposal of existing gymnasium, demolition of part of the building, including disposal.
- 2 demolition and disposal of outdoor facilities reinforced concrete stairways;
- Demolition and disposal of external systems retaining walls, external stairs, etc.
- clearing, dismantling and disposal equipment, heating, ventilation, sanitary, electrical systems diverse;
- approx. 5,316 m
- 1 pc complete demolition and disposal of existing gymnasium including all foundations, deep clearing;
- 1 piece demolition of the building including disposal in the existing connecting building component C to the upper edge of the floor slab;
- approx. 5 300 m
- approx. 5 300 m
- approx. 145 m
- approx. 334 m
- approx. 265 m
- approx. 806 m
- approx. 463 m
- Demolition and disposal of wooden windows, door systems, plastic windows;
- Declaration analyzes on site to determine waste codes and disposal.