Technical thermal insulation 70-00001-2040-406
“* Dates for performing the main performance on the construction site:
Leistungsbeginn 23.02.2024; Leistungsende 30.08.2025
* Description of the procurement:
Air ducts MIWO laminated 40 m2
Air ducts MIWO + sheet metal 105 m2
Air ducts diffusion-tight 30 m2
Mineral wool laminated 100% approx. 1000 m
Mineral wool laminated 100% with sheet metal approx. 250 m
KLT
Dampfdiffusionsdicht approx. 2,000 m
vapour diffusion tight + sheet metal approx. 400 m
SAN
Dampfdiffusionsdicht ca. 700 m
vapour diffusion-tight + sheet metal approx. 170 m