Scaffolding and construction site equipment
Establish construction site facilities including obtaining permits, setting up warning lights and beacons, securing the areas with open and closed construction fences, a total of approx. 150 m. Positioning of a facade scaffolding (approx. 6,500 m 2 ) with extension to the roof catch (approx. 300 m) and pavement widening 30 cm (approx. 3,400 m) and pavement widening 90 cm (approx. 300 m). The scaffolding surfaces must be provided with a protective tarpaulin over the entire height. Access to the scaffolding must be ensured by 5 stair towers and 5 elevator towers with a transport platform for people and material transport. Furthermore, pedestrian tunnels and roller scaffolding are used outdoors. Inside the building there are two room scaffolds (approx. 200 m 2 ) for processing surfaces above stairs.
Establish construction site facilities including obtaining permits, setting up warning lights and beacons, securing the areas with open and closed construction fences, a total of approx. 150 m.
Positioning of a facade scaffolding (approx. 6,500 m 2 ) with extension to the roof catch (approx. 300 m) and pavement widening 30 cm (approx. 3,400 m) and pavement widening 90 cm (approx. 300 m). The scaffolding surfaces must be provided with a protective tarpaulin over the entire height.
Access to the scaffolding must be ensured by 5 stair towers and 5 elevator towers with a transport platform for people and material transport.
Furthermore, pedestrian tunnels and roller scaffolding are used in the outdoor area.
Inside the building there are two room scaffolds (approx. 200 m 2 ) for processing surfaces above stairs.