Development of design documentation for the reconstruction of the gas network - 7 Tasks
Task 1 – Zgierz, Ozorkowska StreetPreparation of design documentation for the reconstruction of the PE 110 mm low-pressure gas pipeline with a length of L = approx. 201 m in Zgierz, Ozorkowska Street and the switching of 1 pc. gas connection in accordance with Technical Conditions No. PSGLO/ZMDZ/ZMSM/144/2022/G/P
Task 2 – Łódź, Malwowa StreetDevelopment of design documentation for the reconstruction of the gas pipeline with connections in the m. Malwowa, Przyrodnicza, Głogowa, Wrzosowa, Żarnowcowa, Julianowska in accordance with Technical Conditions no. PSGLO/ZMDZ/ZMSM/135/2022/G/P
- gas pipeline N/C STAL DN 100/80 mm to gas pipeline Ś/C PE DN 63/110 with length L = approx. 1 307 m
- adaptation of the N/C PE 110/160 mm gas pipeline to the Ś/C gas pipeline with a length of L = approx. 421 m
- PE gas connections 40/25 mm pcs. 56 including connection to the existing gas installation located in the buildings
- switching 19 pcs. Connections
Task 3 – Skierniewice, Prymasowska StreetPreparation of design documentation for the reconstruction of the gas pipeline with connections in Skierniewice, Prymasowska Street, Gałeckiego street in accordance with the Technical Conditions no. PSGLO/ZMDZ/ZMSM/173/2022/G/P
- medium pressure gas pipeline PE 125/110 mm with a length L = approx. 612 m
- gas connections PE 40/25 mm pcs. 10 including connection to the existing gas installation located in the buildings
- switching 7 pcs. Connections
Task 4 – Aleksandrów Łódzki, Piotrkowska StreetDevelopment of design documentation for the reconstruction of the medium pressure PE 125 mm gas pipeline with a length of L = approx. 320 m in m. Aleksandrów Łódzki, Piotrkowska Street on the height of pos. 10/12 to Kilińskiego Street, in accordance with the Technical Conditions no. PSGLO/ZMDZ/ZMSM/158/2022/G
Task 5 – Łódź, Drewnowska StreetDevelopment of design documentation for the reconstruction of the gas pipeline in Łódź, Drewnowska Street from pos. No. 5 to Zachodnia Street in accordance with the Technical Conditions No. PSGLO/ZMDZ/ZMSM/116/2022/G/P
- low pressure gas pipeline PE 125 mm with a length L = approx. 105 m
- PE gas connections 90 mm pcs. 5 including connection to the existing gas installation located in the buildings
- switching 3 pcs. Connections
Task 6 – Łódź, Krakowska StreetPreparation of design documentation for the reconstruction of the gas pipeline in Łódź, Krakowska Street in accordance with the Technical Conditions No. PSGLO/ZMDZ/ZMSM/118/2022/G/P
- low pressure gas pipeline PE 125 mm with a length L = approx. 564 m
- PE gas connections 40 mm pcs. 9 with connection to the existing gas installation located in the buildings
- switching 6 pcs. Connections
Task 7 – Pabianice, Pulaskiego StreetPreparation of design documentation for the reconstruction of the gas pipeline in Pabianice, Pulaskiego Street in accordance with the Technical Conditions No. PSGLO/ZMDZ/ZMSM/169/2022/G/P
- gas pipeline N/C PE DN 125 mm with a length L = approx. 527 m
- gas connections PE 40/63/90 mm pcs. 17 with connection to the existing gas installation located in the buildings
- switching 1 pc. Connections