The existing elementary and regular school is to be brought together on a “campus”. For this reason, a part of the building will be added to the existing regular school. The primary and regular school rooms including administration, canteen, auditorium and other central functions are to be accommodated in this.
The 02 – Gerüstarbeiten
Overview of services
- approx. 2,600 m² working scaffold SW09 incl. 40 weeks of use
- approx. 1,200 m pavement widening B= 0.33m incl. 25 weeks of use
- approx. 475 m interior railing incl. 25 weeks of use
- 5 lattice girders up to 6m incl. transfer of use
- 3 stairwells, single-flight incl. transfer of use
- 1 material hoist incl. transfer of use
- approx. 90 m³ cargo tower for material hoisting incl. transfer of use
- approx. 145 m³ room scaffolding incl. transfer of use
Execution period: approx. CW 19, 2024 to CW 10, 2025