DIN 18384 lightning protection and earthing systems.
Lightning protection for old and new buildings:
- approx. 280 m foundation earth electrode;
- approx. 800 m ring earth electrode;
- approx. 1,200 m of interception and down conductors;
- approx. 30 earth rods;
- approx. 30 interception rods.
Existing lightning protection:
October 24, 2020 to June 18, 2021
Lightning protection cafeteria:
November 9, 2020 to November 15, 2021
A total of 35 working days.