The Montessori Förderkreis Rothenburg od T. e. V. plans to build a new Montessori elementary and middle school with after-school care in BA I and expansion of a single-field sports hall in BA II.
The primary school will have 4, the middle school 6 classes and the after-school care center 2 groups for a total of 213 students.
The property has a total size of 16,680 m² and is planned with ground floor, upper floor and flat roof with extensive roof greening including technical areas for kitchen ventilation. The external dimensions of the building are approximately 68 m (north-south) x 61 m (east-west) x 9 m (h), the gross gross floor area GFA (usually for EC/OG) is 3,590 m² and the gross gross gross volume BRI (normal) 15083 m³. The development takes place via the “Dinkelsbühler Straße” located south of the property.
The basic idea of the design is the connection of 3 building wings with a joint as the center. This forum serves as the heart of the school, which not only connects the 3 building parts, but also the floors with one another via an air space.
The load-bearing structure of the school building is designed as a reinforced concrete frame construction and is to be designed for an increase in all areas.
Overall, the new school is planned as a compact and very economical building. It brings together the currently separate Montessori branches - primary level in the Neusitz district and secondary level in the old town of Rothenburg under one roof.
As part of the new construction of the Montessori School in Rothenburg, the outdoor facilities on the property will be completely rebuilt, an adaptation of the public intersection area and the creation of a kiss & ride zone on the public land adjacent to the south.
The production takes place in five construction phases. Terraces, paths, pavements, walls, enclosures, car parking spaces, a fire fighting experience and equipment are created, and green areas are modeled and greened.
Earth modelling creates landing and landing areas for stay, sports, seating, roads and green spaces. As part of the new installation, the areas adjacent to the building and the connecting paths within walking distance will be paved. The surfaces of the outdoor facilities for school/nursery use are partly produced as water-bound pathways.
The driveways are manufactured in asphalt, paving stones and grass paving stones.
Processing area: approx. 15,000 m²
Earth moving: approx. 5,700 cbm (plus approx. 2,100 m³ available on site. loading and disposing)
Hold/embankment modelling: 2,000 m²
piping: approx. 250 m
Concrete block paster: approx. 2,500 m² (2270)
Asphalt work: approx. 770 m²
Lawn grid 210 m²
water-bound pathway mat: approx. 350 m²
Natural stone wall (block masonry): 130 pcs.
Angle retaining walls: approx. 21 m
Lawn planum/planum: 16,600 m²
Tree plantings: 35 pcs (of which 2 with underfloor quarters)
solitaire plantings: approx. 130 pcs
Shrub plantings: approx. 280 pcs
Hedge planting: approx. 520 pcs
Ground cover plants, grasses, perennials: approx. 1930 pcs.
Bar grid mat fence: approx. 100 m
Chain link fence: 215m approx
Drop protection sand/wood chipper: approx. 330 m²
seeding: approx. 7,800 m²