Bocholter Energie- und Wasserversorgung GmbH (BEW) - hereinafter referred to as AG - was commissioned by the city of Bocholt with the planning and expansion of a nationwide, passive broadband network described in the following chapter. The goal of the state-funded project is the establishment of a future-proof and modern "Fiber to the Building" (FttB) network in the area of the so-called "white spots". All connections that do not have a min. 30 Mbit / s are available in the downstream.
The overall construction of all clusters is scheduled to begin in April 2019 and to be completed by the end of 2021.
All materials required for this are to be provided.
Microcables12,000 meters of micro cable.
Sealing for wall openingsSelf-filling two-component expansion resin for gas- and water-tight sealing of wall openings.