The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— plants containing substances that are hazardous to water,
— pressure vessels (also thermally stressed) and CO
— steam boiler systems,
— power plants,
— gas turbine systems,
— waste heat boiler,
- elevator systems,
— ex-plants,
— ventilation systems,
— machine smoke extraction systems,
— natural smoke extraction systems,
— stationary, non-automatic fire extinguishing systems,
— electrical systems such as high voltage systems, safety-related systems, replacement power sources, fire alarm and alarm systems, safety lighting, safety power supplies, etc.
— storage of incident-relevant substances on safety surfaces
— automatic sliding/revolving doors,
— power-operated gates,
— lifting and crane systems,
— environmental and environmental impact assessments,
— creating damage assessments,
— structural fire protection.
The list is not exhaustive.
Framework contract testing of systems requiring monitoring and testing (SachsenNetze GmbH, district heating)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— plants containing substances that are hazardous to water,
— pressure vessels (also thermally stressed) and CO2 storage tanks,
— elevator systems,
— ex-plants,
— ventilation systems,
— machine smoke extraction systems,
— natural smoke extraction systems,
— stationary, non-automatic fire extinguishing systems,
— electrical systems such as power systems, safety-related systems, replacement power sources, fire alarm and alarm systems, safety lighting, safety power supplies, etc.
— storage of incident-relevant substances on safety surfaces
— automatic sliding/revolving doors,
— power-operated gates,
— lifting and crane systems,
— environmental and environmental impact assessments,
— creating damage assessments,
— Tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV).
The list is not exhaustive.
Framework contract testing of systems requiring monitoring and testing (DREWAG Stadtwerke-Dresden GmbH, Kraftwerke)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— plants containing substances that are hazardous to water,
— pressure vessels (also thermally stressed) and CO
— steam boiler systems,
— waste heat boiler,
— gas turbines,
— elevator systems,
— ex-plants,
— ventilation systems,
— machine smoke extraction systems,
— natural smoke extraction systems,
— stationary, non-automatic fire extinguishing systems,
— electrical systems such as power systems, safety-related systems, replacement power sources, fire alarm and alarm systems, safety lighting, safety power supplies, etc.
— storage of incident-relevant substances on safety surfaces
— automatic sliding/revolving doors,
— power-operated gates,
— lifting and crane systems,
— environmental and environmental impact assessments,
— creating damage assessments,
- Structural fire protection,
— tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV),
— damage assessment.
The list is not exhaustive.
Framework contract testing of systems requiring monitoring and auditing (SachsenNetze HS.HD GmbH)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— pressure vessels (also thermally stressed) and CO
— tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV),
— damage assessment.
The list is not exhaustive.
Framework contract testing of systems requiring monitoring and testing (SachsenEnergie AG)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— elevator systems,
— compressed air systems,
- heating systems,
— escalators,
— tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV),
— damage assessment.
The list is not exhaustive.
Framework contract testing of systems requiring monitoring and auditing (DREWAG Stadtwerke-Dresden GmbH, real estate)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— plants containing substances that are hazardous to water,
— elevator systems,
— ex-plants,
— ventilation systems,
— machine smoke extraction systems,
— natural smoke extraction systems,
— stationary, non-automatic fire extinguishing systems,
— electrical systems such as power systems, safety-related systems, replacement power sources, fire alarm and alarm systems, safety lighting, safety power supplies, etc.
— storage of incident-relevant substances on safety surfaces
— automatic sliding/revolving doors,
— power-operated gates,
— lifting and crane systems,
— environmental and environmental impact assessments,
— creating damage assessments,
— tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV),
— damage assessment.
The list is not exhaustive.
Framework contract testing of systems requiring monitoring and testing (DREWAG Stadtwerke-Dresden GmbH, drinking water)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— plants containing substances that are hazardous to water,
— pressure vessels (also thermally stressed) and CO
— elevator systems,
— ex-plants,
— ventilation systems,
— machine smoke extraction systems,
— natural smoke extraction systems,
— stationary, non-automatic fire extinguishing systems,
— electrical systems such as power systems, safety-related systems, replacement power sources, fire alarm and alarm systems, safety lighting, safety power supplies, etc.
— storage of incident-relevant substances on safety surfaces
— automatic sliding/revolving doors,
— power-operated gates,
— lifting and crane systems,
— environmental and environmental impact assessments,
— creating damage assessments,
— Tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV).
The list is not exhaustive.
Framework agreement testing of systems requiring monitoring and testing (SachsenEnergie Bau GmbH, heat exchanger stations gas drinking water)The scope of services for the systems requiring monitoring and auditing includes:
Testing:
— plants containing substances that are hazardous to water,
— pressure vessels (also thermally stressed) and CO
— elevator systems,
— ex-plants,
— ventilation systems,
— machine smoke extraction systems,
— natural smoke extraction systems,
— stationary, non-automatic fire extinguishing systems,
— electrical systems such as power systems, safety-related systems, replacement power sources, fire alarm and alarm systems, safety lighting, safety power supplies, etc.
— storage of incident-relevant substances on safety surfaces
— automatic sliding/revolving doors,
— power-operated gates,
— lifting and crane systems,
— environmental and environmental impact assessments,
— creating damage assessments,
— Tests before commissioning and re-commissioning (Sections 15 and 16 BetrSichV).
The list is not exhaustive.