The flooring work will begin after the screed work has been completed. The flooring work is carried out on a floor-by-floor basis and includes flooring made of rubber and textile flooring.
The main services are:
- Prepare the subsoil approx. 2,000 m
- R9 rubber floor covering approx. 1,400 m
- R10A rubber flooring approx. 50 m
- Textile floor covering approx. 550 m
- Initial care of the floor covering approx. 2,000 m
The flooring work will begin after the screed work has been completed. The flooring work is carried out on a floor-by-floor basis and includes flooring made of rubber and textile flooring.
The main services are:
- Prepare the subsoil approx. 2,000 m
- R9 rubber floor covering approx. 1,400 m
- R10A rubber flooring approx. 50 m
- Textile floor covering approx. 550 m
- Initial care of the floor covering approx. 2,000 m