This contract concerns structural works. Scope of works: - Demolitions Built volumes: +/- 1000 m3 - Earthworks: +/- 500 M3 - Concrete: +/- 600 M3 - Masonry: +/- 200 M3 - Buried pipes: +/- 300 ML - Grounding of all buildings Start of work Mid-October 2023 Duration of work 130 working days in phases with intermediate delay of 90 days for laying of frameworks.
This contract concerns structural works. Scope of works: - Demolitions Built volumes: +/- 1000 m3 - Earthworks: +/- 500 M3 - Concrete: +/- 600 M3 - Masonry: +/- 200 M3 - Buried pipes: +/- 300 ML - Grounding of all buildings Start of work Mid-October 2023 Duration of work 130 working days in phases with intermediate delay of 90 days for laying of frameworks.