The purpose of this consultation is to provide the necessary services for the construction of the main lift station of 700 m
The contract to be concluded at the end of this procedure shall include the studies and services necessary to carry out the work in accordance with the guarantees entered into by the holder.
It also includes the development, implementation, industrial observation of new facilities and their operation during warranty testing.
Compulsory PES: insurance policy all risks construction site.
The purpose of this consultation is to provide the necessary services for the construction of the main lift station of 700 m
The contract to be concluded at the end of this procedure shall include the studies and services necessary to carry out the work in accordance with the guarantees entered into by the holder.
It also includes the development, implementation, industrial observation of new facilities and their operation during warranty testing.
PSE must be filled in: insurance policy all risks site.