Natural stone work façade
Preparation of damage documentation of remaining façade parts Eaves cornice, in-situ profile, robes 142.5 m
Preparation of damage documentation of remaining façade parts Natural stone base 120 m2
Protection of adjacent areas from contamination 250 m2
Synthetic resin injections, rehabilitation cracks 290 running meters
Basic cleaning - natural stone surfaces 115 m2
Nachreinigung 115 m2
Analysis of natural stone 1 pcs
Sample area intensive cleaning 2 pcs
Sample surface impregnation 2 pcs
Stone addition - crossing, whole stones, limestone, new 5 m2
Renew joints 650 m
Applying graffiti protection 55 m2
Analysis of concrete stone 1 pcs
Analysis of joint mortar 1 pcs
Test mixes for sampling, concrete stone 3 pcs
Sample mixes for sampling, joint mortar 3 pcs
Basic and post-cleaning, concrete stone surfaces 450 running metres
Replace robes 35 pcs
Reprofiling excavation sites up to 0.1m² 220 pcs