Construction of the new school group located on avenue La Motte in Lesquin.
Big workThe works of this lot include:
- site installations - base life intended for all trades according to CCTC prescriptions,
- earthworks,
- platforms under paving,
- The foundations,
- underground pipes / ducts,
- the paving,
- the supported slabs,
- load-bearing and non-load-bearing masonry,
- the reinforced concrete structure,
- miscellaneous works related to the structural work,
- the brick facade cladding and the underside of the exterior staircase, including insulation and angles,
- flocking,
- the flue under paving,
- final cleaning.
Paints - cleaningThe contractor must carry out all painting and wall hanging work necessary for the perfect finish of all exterior and interior works.
These include all ancillary work such as ginning, brushing, sanding, printing, coatings, rust scraping, revision of interior layers, etc ... (unless otherwise stipulated in the specifications), as well as cleaning of the presentation of the works (floors, windows and common areas) for reception and operations prior to reception.
The painter will also have to prepare and install the site specific to his lot in addition to the site installations provided for in the shell lot and listed in the CCTC.
ElevatorThis lot concerns the installation of an elevator.
HVAC - plumbingThe works to be carried out by this lot are as follows:
- heat production by gas condensing boiler,
- space heating by hot water radiators and hot water radiant panels,
- double-flow mechanical ventilation with energy recovery from the extracted air for classrooms, bathrooms, dining hall, offices, multipurpose room and half-board rooms,
- simple flow mechanical ventilation in specific rooms,
- air conditioning of the "computer" room by a direct expansion system,
- extractor hoods in the half-board “cooking” room with compensation box fitted with a hot coil for preheating the fresh air.
An energy recovery system will be set up on the air extracted from the “cooking” room for preheating the compensation air.
ElectricityThe works relating to this lot mainly include:
- the origin of the installations,
- earth circuits and earth electrodes,
- all electrical metering,
- the general low voltage switchboard,
- the divisional tables
- the paths,
- emergency stops,
- the main distribution,
- secondary distribution, force, light and other users,
- normal lighting installations,
- emergency lighting installations,
- various installations and sockets,
- IT installations,
- photovoltaic installations,
- fire alarm systems,
- intrusion alarm systems
- videophone and access control installations,
- charging station for electric vehicle,
- telephone installations,
- time display installations
- ringing and PPMS installations,
- the management of electricity meters.
This list is not exhaustive.
CookedThe work includes: supply and installation of specific kitchen equipment according to the listing and description of the CCTP.
VRDThe work described in this description is necessary in order to carry out the exterior development work for this operation.
They concern:
- site installations,
- the demolition of roads, infrastructure works and miscellaneous located in the rights-of-way of future roads, parking lots, sidewalks, pedestrian areas and green spaces,
- work to remove various furniture,
- borders and gutters,
- the construction of roads (parking lots, roads, pedestrian circulation),
- sanitation of rainwater and wastewater,
- the realization of various works, the upgrading of manholes and lockouts,
- the trench for various networks,
- treatment of various networks (EDF, telecommunications, water supply and lighting),
- the treatment of green spaces,
- tests, checks and proofing plans.
Green spacesThe work will include:
- studies and execution plans,
- preparatory work, site installation, cleaning,
- reception of the levels of the topsoil support, from the earthwork platform to the roadwork and various networks at - average 30 cm,
- fine leveling, adjustment and compaction of the subforms of the planted areas,
- supply and approval by the MO of control samples of topsoil,
- implementation of topsoil,
- soil preparation for planting and sowing, including analysis and amendment of the topsoil,
- supply for the work, installation of plants (trees, grasses, seedlings, etc.),
- construction of tree planting pits, removal of excess fill,
- supply and installation of root ball anchors and staking, BRF type mulching for planted areas, non-freezing vents for manual watering, and sprinkler watering,
- maintenance of plantations, replacement of plants.
Waterproofing - coverThe work of this lot will include:
- waterproofing including upstands and connection to outlets,
- membrane covers,
- insulation,
- skylights,
- wall coverings and protective flashings, simple or expanding,
- rainwater drainage systems, with overflow,
- sealing constraints,
- the execution of connection works on the walls (flashing, caulking, and their perfect finish),
- accessories, etc.
This list of works is not exhaustive.
Wood structure - facade - claddingThe work relating to this lot concerns the supply and installation of:
- roof boxes,
- beam structures in glued laminated timber in spruce wood,
- caps,
- Interior wood frame walls (Mob),
- exterior timber frame walls,
- gable structures in glued laminated timber in spruce wood,
- cladding.
Exterior joinery - locksmithThe work relating to this lot concerns all glazed frames, curtain walls, glazed facades, exterior blinds, glazed and solid exterior doors, guardrails and all the works described.
plasteringThe work will include:
- plasterboard lining and cladding partitions,
- technical ducts,
- Placostil partitions or equivalent,
- plaster fittings,
- plastic U for partitions and linings in damp rooms,
- Phaltex tapes according to DTU requirements,
- plasterboard finishing coatings including after passage of other trades (see CCTC),
- reinforcing wood furs for frame fixings,
- metallic reinforcing profiles for washbasins, basins, lifting bars, mirrors, TV cabinets in technical rooms, etc.
- Frame reinforcements, special Placoplatre piece, type sanitary support for suspended bowls (for WC not suspended on concrete ducts),
- reinforcements and treatment of salient angles,
- earthing of metal partitions, etc.
- Tracing of traffic axes in blue, including maintenance up to the laying of glued flexible floors.
False ceilingsThe work of this lot will include:
- smooth plasterboard ceilings,
- perforated plasterboard ceilings,
- suspended ceilings with mineral fiber tiles,
- fallout from ceilings,
- thermal and acoustic insulation on ceilings,
- the supply and installation of metal frames and the devices necessary for their attachment to the supporting structure,
- the supply and installation of the tiles, constituting the ceiling itself, including all the hanging systems, fixings and links (anchors, clips, slides, slides, etc.),
- protection by galvanizing, electro-zinc plating, anodizing or organic coating of all metallic elements.
Interior joineryThe work of this lot will include:
- ordinary, glazed, flame-retardant, fire-rated and sliding door units,
- the locks including management of the organization chart,
- temporary lock barrels,
- door protections,
- ordinary frames, flame arresters and fire barriers,
- technical hatches,
- wooden plinths,
- the facades of technical ducts,
- the pipe covers,
- benches - coat hooks - classroom board etc.
- The chassis shelves,
- acoustic covers,
- the coverings of expansion joints,
- the provisional numbering of the parts, during the construction phase, (in the sash rebate),
- as well as all necessary interior woodwork services provided or not in this CCTP.
8The work of this lot will include:
- verification and reception of supports and levels,
- the supply, storage, installation and installation of materials,
- cleaning of the structures before reception,
- the removal of craons resulting from its intervention,
- the connections, cuts and holes necessary for the perfect completion of this work,
- supply and installation of expansion joints, sawn timber required for their preparation,
- the protection of its works for the duration of the works until acceptance,
- the contractor must take all measures to avoid any disturbances that could be caused by the effects of expansion or withdrawal.
Tile lifting or any other damage that may result from it must be repaired during the entire warranty period at its expense.
Flexible floors (CGD) - floor resinThe work of this lot will include:
- verification and reception of supports and levels,
- layout plans, samples and technical sheets,
- the supply, storage, installation and installation of materials,
- cleaning of the structures before reception,
- the removal of craons resulting from its intervention,
- the connections, cuts and holes necessary for the perfect completion of this work,
- supply and installation of expansion joints, sawn timber required for their preparation,
- the protection of its works for the duration of the work and the replacement of damage at the expense of the company until acceptance,
- the contractor must take all measures to avoid any possible disturbances,
The effects of expansion or withdrawal. Defects must be repaired during the entire warranty period at its expense.