Freiberger Mulde, HWS Döbeln, heraldic henschanlage, construction phase 2, construction of HS facilities between ship bridge and bridge Schillerstraße
Intermediate consumption:
Explosive ordnance exploration approx. 3,000 m² as area sounding and 3,500 m as depth sounding, pipeline exploration and rerouting, construction site clearance, traffic safety and diversion
Hochwasserschutzwand:
approx. 4,000 m³ working levels, partly in the water, phased dismantling
2 pieces flood for rainwater discharge
approx. 2,000 m bored piles, Ø 120 cm as overlapped bored pile wall
ca. 50 m² Trägerbohlverbau
ca. 30 m³ Düsenstrahlkörper
approx. 3,000 m³ excavated earth and backfill
approx. 400 m³ reinforced concrete for WU components, ÜK 2, ZTV-Ing
Equipment or equipment with:
HWS gate, railing, dam beams, dam beam box as precast reinforced concrete element
road construction:
ca. 220 m³ Frostschutzschichten
ca. 350 m² Asphaltbefestigung
ca. 250 m² Pflasterdecke (Betonsteine, Mosaikpflaster)
Randeinfassungen, Straßenabläufe, Kastenrinnen