Construction of the third Separate Digester (WKFZ) in the sewage treatment plant
Construction of a pipeline draining fermented sludge from digester No. 3 (new WKFZ No. 3) to the fermented sludge tank in front of centrifuges
Expansion and/or replacement of sludge exchangers
Expansion and/or replacement of sludge recirculation pumping stations
Expansion of the existing I&C system with new facilities and modernization of existing facilities
Construction of a Separate Fermentation Chamber at the "Centralna" Sewage Treatment Plant in Toruń
The subject of this contract includes the execution of the following construction works at the Central Sewage Treatment Plant in Toruń:
Construction of the third Separate Digester (WKFZ) in the sewage treatment plant
Construction of a pipeline draining fermented sludge from digester No. 3 (new WKFZ No. 3) to the fermented sludge tank in front of centrifuges
Expansion and/or replacement of sludge exchangers
Expansion and/or replacement of sludge recirculation pumping stations
Expansion of the existing I&C system with new facilities and modernization of existing facilities