At the start of the contract, Trustrup has 2 tracks, of which only track 1 has a platform and driving current. Thus, Track 2, which is scheduled for 2018, is not used. The contract includes the establishment of a new platform between tracks 1 and 2 at Trustrup station, including among other things. foundation, platform, coating, lighting, drainage, track crossing as well as handling and mounting of contractor deliveries such as soft drinks and platform front. The contract also includes, among other things, the establishment of routing routes for new and existing cables, the establishment of new wiring. The contract includes a new runway system for track 2, including, among other things, the supply and installation of foundations and masts, suspension and overhead lines, with integration into existing overhead line systems and the execution of tests.
The construction work will primarily take place at Trustrup Station. include:
- Establishment of a new platform, including foundation, paving, upholstery and drainage works,
- Establishing a ramp and crossing over tracks,
- Road flow works, including foundation and establishment of road flow masts, suspension of road wire and integration of road power plants into existing road power plants.