The contract includes the delivery and commissioning of four prefabricated sewage pump stations with prefabricated superstructures. The contract also includes activation and commissioning period in accordance with the water and sewage standard service contract and service contract for delivered pump stations.
This contract was first announced in September 2020 but due to technical errors with the extension of the deadline it had to be cancelled and now announced again. The deadline was due to be extended due to changes to the sump at PA 30 Midtgård. The contract basis describes that the pump station PA 30 Midtgård will be built on-site, this will be struck out and changed to a completely new pump station. New version of the contract basis will be published as soon as it is ready.
The project will be implemented as two contracts: one contract (this contract) with delivery of prefabricated pump stations and one built on site, and a contract for the excavation works.
This contract includes delivery and commissioning of four sewage pump stations at Kvaløya.
There are four existing pump stations, PA 19 Oladalen, PA 30 Midtgård, PA 31 Åsland and PA 23 Djupelva that will be demolished and replaced with new pump stations.
PA 23 is offered as an option as there are uncertainties around land acquisition and rights. I.e., PA 23 can be ordered a while after the other stations, alternatively, it might not be ordered at all.
The contract also includes activation and commissioning period in accordance with the water and sewage standard service contract and service contract for delivered pump stations.