General renovation of the east wing of the HIP secondary school in Calw:
The east wing of the Heinrich Perrot secondary school in Calw is the last building of the school complex in the city centre, which
has not yet undergone a general renovation. For this purpose, the entire east wing will be cleared. And the
The school moves into additional space in the west wing and in the neighboring schools, as well as in containers that have yet to be set up in the schoolyard of the neighboring Hermann Hesse Gymnasium. The refurbishment includes all four
Floors of the east wing.
It is planned to start the work in November 2023 with the demolition work and after about 18 months
in May 2025.
Plumbing + fire extinguishing system "dry":
Dismantling approx. 35 pieces of furnishings (WT's, WC's, urinals, GTC's, with fittings incl. accessories).
Dismantling of a drinking water distributor + prov. TW supply stock
Dismantling approx. 300 m drinking water + fire extinguishing pipes up to DN80
Dismantling approx. 150 m of sewage pipes up to DN125
Dismantling 4 pcs combination hydrant/fire extinguisher boxes
approx. 30 pcs furnishings (WT's, WC's, urinals, AG's, showers with fittings and accessories).
1 St Trinkwasserverteiler
approx. 500 m drinking water pipe with insulation
approx. 200 m sewage pipe with insulation
approx. 40 m fire extinguishing pipe up to DN80 incl. feed + 4 pcs extraction boxes
approx. 70 fire protection bushings
approx. 70 core boreholes up to DN250