B480n OU Bad Wünnenberg, new construction of the overflight aids in the area of the Aftetalbrücke (BW3).
- approx. 250 m
- approx. 450 m
- approx. 216 m drilling level including all earthworks,
- approx. 198 m drilling level along the overflight aids south of the bridge,
- approx. 400 m bored piles D = 80 cm,
- approx. 106 steel posts for overflight aid h = 4 m,
- approx. 273 steel posts for overflight aid on parapet (h = 2.75),
- approx. 650 m
- approx. 1470 m
- approx. 850 m