Painting and varnishing work (2nd construction phase)
The building is divided into four halls and ancillary areas. Hall A is a triple sports hall (27x45x7m), which is planned as a meeting place. Hall B (12x12x4m) is used as a gymnastics hall and Hall C & D are one-and-a-half technical halls (18x36x5m). In the ancillary areas there is an equipment room, a medical room, a cleaning product/storage room, and a changing room for each part of the hall. The changing room block is divided into a women's and a men's area, as well as storage rooms.
The flooring work (2.BA) will take place in the adjoining rooms of Halls C & D.
- masking of components 1,047.420 m
- Cover floor areas with Malerflies 2.390,700 m2
- Clean old coating 1.374,920 m2
- Repair old coating 350,000 m2
- Coating, dispersion 1,374,920 m2 + 504,210 m2
- Filling, dispersion, interior ceiling 550,000 m2
- permanently elastic joints 1,047.420 m
- Dispersion painting ceilings 550,000 m2
- Paint steel block frames with skylight 35,000 pcs