Description:
Construction of bicycle and pedestrian bridge R71 x Elfde-Liniestraat

The contract mainly comprises:

- Construction of a bicycle and pedestrian bridge as indicated on the contract documents. The contractor must only include the execution modalities, namely the assembly study, the preparation of working drawings for production, etc.;

- Measuring the existing situation;

- Grubbing up trees and plantings;

- Preparing zones for construction;

- Construction and demolition works;

- Carefully break up all kinds of structures and elements such as statue at PXL;

- Selective milling of tar asphalt;

- Thermal cleaning of tar asphalt;

- Demolition of existing pavements;

- Earthmoving and land supply;

- Earthworks for road construction;

- Embankments;

- Construction of sewerage;

- Installation of new street eddies and adjustments to existing ones;

- Installation of new inspection wells and adjustments to existing ones;

- Construction of new roads in asphalt and unreinforced concrete;

- Construction of sewerage in groundwater;

- Delivery and installation of a steel bicycle and pedestrian bridge with associated foundations and appurtenances in a busy traffic environment;

- Supplying and installing all kinds of elements for the placement of the lighting such as cable entry pipes, recesses, through openings, attachment points, ...;

- Installation of shielding structures;

- Installation of transition, initial and safety structures;

- Placement of signage;

- Construction and breaking up of temporary crossings;

- Installing, moving, renting, maintaining and removing site signage;

- Apply temporary and permanent markings;

- Formatting an as-built file;

- Coordination and coordination with other works in progress at the same time;

- maintenance of the works during the guarantee period

The contract mainly comprises:

- Construction of a bicycle and pedestrian bridge as indicated on the contract documents. The contractor must only include the execution modalities, namely the assembly study, the preparation of working drawings for production, etc.;

- Measuring the existing situation;

- Grubbing up trees and plantings;

- Preparing zones for construction;

- Construction and demolition works;

- Carefully break up all kinds of structures and elements such as statue at PXL;

- Selective milling of tar asphalt;

- Thermal cleaning of tar asphalt;

- Demolition of existing pavements;

- Earthmoving and land supply;

- Earthworks for road construction;

- Embankments;

- Construction of sewerage;

- Installation of new street eddies and adjustments to existing ones;

- Installation of new inspection wells and adjustments to existing ones;

- Construction of new roads in asphalt and unreinforced concrete;

- Construction of sewerage in groundwater;

- Delivery and installation of a steel bicycle and pedestrian bridge with associated foundations and appurtenances in a busy traffic environment;

- Supplying and installing all kinds of elements for the placement of the lighting such as cable entry pipes, recesses, through openings, attachment points, ...;

- Installation of shielding structures;

- Installation of transition, initial and safety structures;

- Placement of signage;

- Construction and breaking up of temporary crossings;

- Installing, moving, renting, maintaining and removing site signage;

- Apply temporary and permanent markings;

- Formatting an as-built file;

- Coordination and coordination with other works in progress at the same time;

- maintenance of the works during the guarantee period