Flooring work according to DIN 18365 in the existing building (cultural monument)
Flooring work according to DIN 18365 in office and event areas in the existing building (cultural monument), consisting of:
Approx. 380 m² Delivery, preparatory work and new installation of rubber flooring incl. skirting boards
Approx. 830 m² Delivery, preparatory work and new installation of needle felt flooring incl. skirting boards
The execution of the work is expected to take 4 weeks (start: 9th week 2024, end: 14th week 2024).
Due to complex dependencies, continuous processing cannot be assumed.