Railway, road and canal construction
Line 302: Barrier-free expansion of the Watermanns Weg stop in Bochum
Track construction:
-Installation of 2 turnouts and one-time turning in weekend work.
-Removal and new construction of approx. 350 meters of double track.
Canal construction:
-Lateral shaft extension made of reinforced concrete in size 2*4 meters, depth 2.5 meters.
Stadtwerke Bochum:
-Renewal of water and gas pipeline DN 50 and 100 or DN 50 and 150 to
a length of approx. 200 meters
road construction:
-Expansion of 2 low-floor stops.
-Two-sided sidewalk renewal on approx. 2300 m²
- Renewal of the curbs to approx. 400 meters
- Ceiling renovation on approx. 2300 m²
Metal construction.
–Delivery and construction of 2 xenon waiting halls.